Community involvement in the Lindfield Village Green Project

Council has worked closely with the Lindfield Community in developing plans for the Village Green.

Below is a summary of community engagement activities we have undertaken since the project began in 2014. This community involvement will continue as the project progresses.

March 2018 to April 2018  Assessment of the amended development application -  public notification and consultation process
February 2018 One on one briefing with local building owners
Feb 2017 Half day on site information session
Dec 2016 to March 2017 Assessment of development application - public notification and consultation process 
August / September 2016 Briefings with surrounding with local businesses and building owners
March / April 2016 Face to face stakeholder meetings with local businesses, building owners and interested parties 
September 2015 On site information session
July 2015 Briefings with local businesses and building owners
March to May 2015

Activate Lindfield  - Village Green Public Exhibition of 3 Concept Design Options. Aim of process was for public to select its preferred option. Activities included:

  • Community Day: 21 March 2015
  • On-site mobile exhibition space at Tryon Road Lindfield displaying three alternative preliminary designs staffed by project management team
  • Flyers sent 8,032 residents in Lindfield, Roseville and Killara
  • Opt in Workshop
  • Recruited workshop
  • Online engagement portal – nearly 5k visitors
March 2015

Public Exhibition Launch event

  • Included mobile exhibition space
  • Community activities  
February 2014 “Activate Lindfield Family Fun Day”

Designed to commence the conversation with local residents, shop users and businesses on the new village green planned for Lindfield.

2014 to present  Activate Lindfield e-newsletter, 20 newsletters sent