The following table lists roadworks being undertaken by Ku-ring-gai Council (and from time to time, some RMS work on major roads in the Council area). For enquiries regarding works on these roads contact us. 

Willis Avenue    

Gordon No works currently scheduled
East Killara No works currently scheduled No works currently scheduled.
Killara Culworth Avenue Road resurfacing scheduled for April 2018.
   Pacific Highway (between Spencer Road and Marian Street)  RMS will be repairing concrete slabs and repainting road markings. They will be will be on site for one shift between Monday 29 January and Wednesday 28 February, with work hours on Mon - Thurs between 8pm - 5am. There will be temporary traffic changes during work to ensure the work zone is safe. Roadworks being carried out by RMS.

 

East Lindfield Wellington Road (Carlyle Road-Ulmarra Place) Service lowering to commence in preparation for road resurfacing
Lindfield Dangar Street

Service lowering completed. Road resurfacing scheduled for late January/early February 2018.

  Mackenzie Street Service lowering completed. Road resurfacing scheduled for late January/early February 2018
Slade Avenue Road resurfacing completed.
  Smith Street Service lowering completed. Road resurfacing scheduled for late January/early February 2018 
 Pymble

 

Trafalgar Avenue Road resurfacing dates to be confirmed.
Roseville  Victoria Street Investigating and repairing wastewater pipes and maintenance holes. Work will take place periodically from January to June 2018 (between work hours 7am - 6pm Monday to Friday and 8am - 1pm on Saturday). It is expected there will be an increase in noise, odour and vehicle movements as well as temporary changes to pedestrian and traffic movements. Works being carried out by Sydney Water. 
St Ives Mona Vale Road (100 metres north of Woodbury Road)  RMS will be removing and replacing small sections of asphalt and repainting road markings. Works will be completed on site for one shift between Thursday 22 February and Thursday 8 March, on Sun - Thurs between 8pm - 5am. There will be temporary traffic changes during our work hours to ensure the work zone is safe. Roadworks being carried out by RMS.
St Ives Chase    No works currently scheduled. No works currently scheduled

Turramurra

Timaru Street Road resurfacing to be completed in 2017/18 - exact dates not yet scheduled
  Warragal Road Road resurfacing to be completed in 2017/18 - exact dates not yet scheduled
North Turramurra No works currently scheduled No works currently scheduled
South Turramurra Maxwell Street (Turra Street to Buller Street) Road resurfacing scheduled for late January 2018.
  Musgrave Street Road resurfacing scheduled for December 2018. 
Wahroonga Clissold Avenue Road resurfacing scheduled for February 2018
  Cherrywood Avenue Road resurfacing scheduled for February 2018 
  Lucinda Avenue

Road resurfacing to be carried out 22 to 24 January. During this time, the section of Lucinda Avenue, from Eastbourne to Fox Valley Road will be closed in both directions. Residents along the affected section have been advised. A detour will be in place for affected traffic. The works on Lucinda Avenue will be completed by 24 January, 2018. Please note: Eastbourne Avenue will also be closed for partial resurfacing on 22 and 23 January (see below for details)

  Eastbourne Avenue/Seaton Avenue Road resurfacing to be carried out on Tuesday 23 and Wednesday 24 January for resurfacing and the road will be closed. During this time, vehicles travelling along Eastbourne Avenue from Pennant Hills Road side, will not able to continue through to Fox Valley Road and will be detoured back. Eastbourne Avenue residents have been advised.
  Kokoda Avenue Road resurfacing scheduled for February 2018.
  Randolph Street and Young Street Road resurfacing scheduled for April 2017

The Comenarra Parkway (two sections)

Road resurfacing night works on two sections of The Comenarra Parkway - dates to be confirmed:

  • Section 1 - From Browns Road to boundary with Hornsby Council
  • Section 2 - From south of Jordan Road to Fox Valley Road
  Millewa Avenue (between Illoura Ave and Warrawee Ave) Single lane closure until mid-February 2018 due to Sydney Water main breakage. Traffic will be controlled via temporary traffic lights until road can be restored.
Pacific Highway (between Neringah Avenue South & Redleaf Avenue) Essential roadworks being carried out in approximately three night shifts (between 8pm and 5am, Sunday to Thursday) between 3 January and 31 January. Work is expected to be noisy. Works being carried out by Sydney Water.
  Pacific Highway (between intersections of Fox Valley Road and Edwards Road) and Pennant Hills Road Roads and Maritime Services will be modifying existing in-road sensors and adding additional sensors. There will be 36 shifts between 15 January and 26 February 2018, excluding public holidays, weather permitting. Night work hours will be between 9pm and 5am from Sunday to Friday. Day work hours will be between 7am and 5pm Monday to Friday and 9am and 1pm on Saturday. The work will be noisy at times but everything will be done to minimise the impacts. There will be temporary traffic changes during work hours to ensure a safe work zone.
  Woonona Ave Investigating and repairing wastewater pipes and maintenance holes. Work will take place periodically from January - June 2018 (between work hours 7am - 6pm Monday to Friday and 8am - 1pm on Saturday). It is expected there will be an increase in noise, odour and vehicle movements as well as temporary changes to pedestrian and traffic movements. Works being carried out by Sydney Water.
 Warrawee Mitchell Crescent Road resurfacing completed
  Rothwell Road (#44-Mitchell Crescent) Road resurfacing completed
West Pymble Ramsay Avenue Road resurfacing scheduled for early 2018.

The following roads are under the control of the Roads & Maritime Services (RMS).  For all enquiries regarding works on these roads contact the RMS Transport Management Centre on 131 700:

  • Pacific Highway
  • Ryde Road
  • Mona Vale Road
  • Boundary Road (Pacific Highway to Babbage Road)
  • Babbage Road (Boundary Road to Warringah Road)
  • Warringah Road